Notice to Amend Approved
Voluntary Management Proposal
Sections 17 and 44 of the Contaminated Land Management Act 1997
The Council of the City of Sydney ACN 22 636 550 790
GPO Box 1591
Sydney NSW 2000
Attention: The Proper Officer
Amendment Notice No. 20254423; Declaration No. 20181108; Area No. 3433
The Environment Protection Authority (EPA) has issued this Notice to Amend Approved Voluntary Management Proposal (Amendment Notice) to notify you of amendments to the Notice of Approved Voluntary Management Proposal No. 20241709 issued on 21 November 2024 (Original Notice). Further information is set out below.
Please read this Amendment Notice carefully and carry out the actions required. If you have any queries about the matter, please contact info@epa.nsw.gov.au or (02) 9995 5618.
A. The EPA is responsible for administration and enforcement of the Contaminated Land Management Act 1997 (Act) and has issued this Amendment Notice under s 17 and 44 of the Act.
B. The land to which this Amendment Notice applies is Sydney Park and all adjacent pathways and roadways, as shown bounded in blue on the attached map (Land).
C. The Land was declared on 25 February 2019 as significantly contaminated land by Declaration No. 20181108 under s 11 of the Act. The Land has also been the subject an Approved Voluntary Management Proposal as specified in the Original Notice issued under s 17 of the Act.
D. The Original Notice approved the Voluntary Management Proposal, dated 21 November 2024, in respect of The Council of the City of Sydney (Approved Party). This Amendment Notice applies to the Approved Party.
E. A copy of the Original Notice (No. 20241709) showing the required actions can be accessed on the Contaminated Land Record of Notices on the EPA’s website at https://apps.epa.nsw.gov.au/prclmapp/searchregister.aspx.
F. The purpose of the amendment is to request extension for deliverable items in the Approved Voluntary Management Proposal to enable The Council of the City of Sydney to undertake procurement processes for the work.
G. The EPA is satisfied that the terms of the approved voluntary management proposal, as modified by this Amendment Notice, are appropriate.
H. This Amendment Notice is taken to be made under the same provisions of the Act as the Original Notice.
The Original Notice is amended as set out below and has effect inclusive of these amendments.
1. Replace The Key Milestones for Investigation, Remediation and other actions (Part 3 Item 3) with the following amended deadlines:
|
Works |
Original Deadline |
Revised Deadline |
|
T4. Assessment of existing gas mitigation systems along the western boundary of the site and in the northern carpark |
30 Sept 2025 |
27 Feb 2026 |
|
T10. Develop a risk-based, Landfill Gas monitoring program. |
30 June 2025 |
30 Sept 2025 |
|
T12. One-off source analysis of gas collected at subsurface well PW-BH37 and service pit EX527, and investigation of feasible locations for installation of additional monitoring wells. |
N/A |
30 Sept 2026 |
2. All other conditions in the Original Notice remain the same and continue to apply in conjunction with any amended and new conditions imposed under this Amendment Notice.
[Signed 15 October 2025]
George Orel
Unit Head - Regulatory Operations
NSW Environment Protection Authority
(by delegation)
Date of this Notice: 15 October 2025
By Email
INFORMATION ABOUT THIS NOTICE
Management order
Under section 17(6) of the Act, the EPA may serve a management order in relation to significantly contaminated land the subject of an approved voluntary management proposal on an approved party to the proposal, if in the opinion of the EPA, the terms of the approved proposal are not carried out, or the management order relates to a matter that is not adequately addressed by the proposal, or its approval of the proposal was given on the basis of false or misleading information.
Cost Recovery
Section 34 of the Act allows the EPA to recover its costs in connection with assessing and settling the terms of, monitoring actions under, or seeking compliance with, an approved voluntary management proposal. The EPA may also recover the costs of any other matter associated with or incidental to these matters, or any other matter prescribed by the regulations.
Amendment or repeal
This notice may be amended or repealed by subsequent notices.
Cessation of the approved voluntary management proposal
A proposal ceases to be an approved voluntary management proposal if the EPA serves a notice in writing on each approved party stating that it is satisfied that the terms of the proposal have all been carried out or withdrawing its approval of the proposal. The proposal will cease at the time specified in the notice or if no time is specified, at the time the notice is served on each approved party.
Information recorded by the EPA
Section 58 of the Act requires the EPA to maintain a public record. A copy of this notice will be included in the public record and is available at the principal office of the EPA and on the EPA’s website.
Information recorded by councils
Section 59(1)(c) of the Act requires the EPA inform the relevant local council of this notice. A planning certificate issued under s 10.7 of the Environmental Planning and Assessment Act 1979 must specify if the land to which the certificate relates is the subject of an approved voluntary management proposal at the date when the certificate is issued. If a council includes advice in a planning certificate regarding an approved voluntary management proposal that no longer applies to the Land, it is to make it clear on the planning certificate that the proposal no longer applies.
Relationship to other regulatory instruments
This notice does not affect the provisions of any relevant environmental planning instruments which apply to the Land or provisions of any other environment protection legislation administered by the EPA.
Guidelines made or approved under s 105 of the Act
All the investigation or remediation works must be carried out in accordance with guidelines made or approved under s 105 of the Act. See https://www.epa.nsw.gov.au/your-environment/contaminated-land/statutory-guidelines.
Previous regulatory instrument
As of 1 July 2009, all current declarations of investigation area and declarations of remediation site are taken to be declarations of significantly contaminated land, all current investigation orders and remediation orders are taken to be management orders and all current agreed voluntary investigation proposals and agreed voluntary remediation proposals are taken to be approved voluntary management proposals.